Expansion and Improvement Works for Ground Floor (and First Floor) at Laboratory Animal Services Centre

To facilitate submission of consent application to Buildings Department, the following preparation works will be carried out at Shanghai Fraternity Association Research Services Centre at Eastern Campus.
1. Hammer test works at Rooms G05-G06;
2. Opening up inspection at Room G04;
3. Removal of existing steel structure at Room G04;
The works areas will be fenced off for construction works from 11 March 2024 to 4 April 2024. Please refer to below diagram for the works location. We apologize for any inconvenience caused.

擴建及改善地下(及一樓)實驗動物中心工程

為配合團隊向屋宇署申請同意展開建築工程, 以下位於上海總會科研技術中心的預備工序必須預先進行。
1. G05-G06室錘敲測試;
2. G04室開鑿檢查;
3. G04室清拆現有金屬結構;
相關工程將於2024年3月11日至2024年4月4日加設圍欄以便施工。施工地點請參閱下圖, 工程期間引起之不便, 敬請原諒。